Transportation of Project cargoes for Alchevs'k Metallurgical Integrated Works

In 2006 OJSC "Alchevs'k Metallurgical Integrated Works" which is within the structure of "Industrial Union of Donbas" became the applicant for transportation of oversized equipment for needs these integrated works. The contract on equipment delivery with French firm "AIR LIQUID ENGINEERING" was concluded on terms CIF port of Mariupol'. Then the set of equipment for construction of "oxygen converter" workshop had to be delivered onto the territory of integrated works in Alchevs'k. Yugintertrans was the General forwarder when transporting this cargo from port of Mariupol' to the object in construction on the territory of "Alchevs'k Metallurgical Integrated Works". The delivery of the equipment was effected from France with vessel consignments through Mariupol' trade port. In addition to other equipment which should be transported the contract stipulated the delivery of 32 units of superoversized equipment having the following features:

Description of equipment Length
(ñì)
Width (cm) Height (ñì) Weight
kg.
Number of units Transportation method, Oversizing extent
Tower 1920 440 440 70 000 2 railway transportation,
super oversized
Tower 3309 464 462 98 000 2 railway transportation,
long, super oversized
Tower 3580 340 340 46 000 2 railway transportation,
long, side oversized
Tower 3182 340 340 54 000 2 railway transportation,
long, side oversized
Absorber 1670 440 440 58 800 4 railway transportation,
super oversized
Air booster compressor 445 240 357 18 850 2 road transportation
Turbine booster 470 280 344 6 380 2 road transportation
Electric heater 370 298 345 14 050 2 road transportation
Tower 705 503 507 42 000 2 road transportation
Water tower 750 488 500 25 800 2 road transportation
Water tower 786 472 504 16 100 2 road transportation
Water tower 905 460 494 22 000 2 road transportation
Overcooler 567 495 305 14 180 2 road transportation
Condenser 564 474 409 18 910 2 road transportation
Motor of booster compressor 411 391 305 21 700 2 road transportation

When preparing the project of this transportation by the enterprise Yugintertrans together with its partners the following steps were taken:

Railway transportation

  • Oversized equipment loading and fastening methods were developed and approved for special railway rolling stock.
  • The schedule of the cargo passing and movement from station Mariupol' to station Komunars'k (260 km) was agreed with Donets'k Railway.
  • Together with our partners the cargo unloading in port of Mariupol' was arranged.
  • The special cargo fastening accessories were developed and made for rolling stock.
Taking into account of super oversized equipment, the shipments were effected only with separate locomotive. The measures were taken in order to provide for conditions of cargo passing through Donets'k Railway, with taking of the contact system voltage along the entire route and dismantling of the contact suspension on some track sections.


Photo. Loading of super oversized cargo in port of Mariupol' onto the rolling stock.

Road transportation


Photo. Loading of super oversized cargo onto the lowbad trailer in port of Mariupol'

As the geometric parameters of some cargoes did not allow to transport them along the railway, their delivery was effected using special road transport. It should be noted, that the total height of road trains carrying cargo laid within 6.0 metres that significantly complicated the passing of railway crossroads, artificial constructions, bridges and power mainlines. The following steps were taken:
  • Verification of the route and approval of this route with all interested organizations.
  • Temporary switching off of the power mainlines along the entire route of road trains was arranged.
  • The schedule of the passing by railway-crossing and the switching off the contact system on their route was agreed.
  • The convoy by the state traffic police along the entire route was arranged.
  • The roadway on problematic sections was put in appropriate order.
  • Accident causing trees were cut off on the lowbed trailers route.
  • The temporary railway crossroad was built in village of Pereval'ne.